When the Dallas-Fort Worth Rolex location sought to enhance operational efficiency, Evolution Mechanical was tapped to retrofit its existing infrastructure with the installation of a second chiller – critical to supporting Rolex’s high standards of performance and reliability.
Solutions:
Infrastructure Integration
• Installed a new chiller that seamlessly integrated into the site’s existing plumbing and water systems, ensuring minimal disruption.
Accelerated Project Timeline
• Prefabrication of the chiller’s structural frame reduced street closure durations and expedited the overall project timeline.
Design and Functionality Alignment
• Architectural updates harmonized the chiller housing with the building’s exterior while maintaining full operational functionality.
Preventative Maintenance Enhancements
• Implemented an updated maintenance plan to ensure the system operates at peak performance with minimal interruptions.
Business Outcomes:
Faster Completion Amid Challenges – Complications with the original chiller’s capacity arose during the project, but proactive coordination among Evolution Mechanical, Rolex, and project stakeholders ensured all preparations were completed ahead of the new chiller’s arrival. The installation was completed in just two weeks, restoring full operational capacity.
Operational Resilience – The addition of a second chiller allows the Dallas-Fort Worth location to act as a backup hub for other Rolex data centers, providing critical support during system maintenance or repairs at other facilities.
Long-Term Cost Savings – Enhanced system efficiency reduces operational costs. Preventative maintenance agreements ensure long-term reliability, minimizing potential downtime and disruptions.